Price River Water Improvement District - Wastewater Treatment Plant Rehabilitation Project

This project involved rehabilitating the existing wastewater treatment plant. There was a significant amount of mechanical work - replacing aging valves and piping, upgrading the existing HVAC system, burner equipment and digester piping. Alder Construction also replaced the existing digester lids to complete this project scope.

Project Details

Project Location: Price, Utah
Project Start: May 2011
Project Completion: July 2012
Contract Size: $ 1,359,000
Site Superintendent: Tony Siaperas
Project Manager: Val Martin
Owner: Price River Water Improvement District
Engineer: Water Works Engineers